Schedule for the Appalachian Corridor Segment

This schedule with dates has been included for a more in-depth understanding
of how long it takes to implement a project.

STEP 1 PLANNING, ENVIRONMENTAL OVERVIEW APRIL 2000 - AUG 2000
STEP 2¹ PUBLIC MEETINGS JUNE 2000
STEP 3¹ IDENTIFY "BEST" ALTERNATIVES
PUBLIC MEETING
NOV 2000 - DEC 2000
JAN 18, 2001
STEP 4 FULL SCALE ENVIRONMENTAL IMPACT STATEMENT DEC 2000 - JAN 2002
STEP 5¹ PUBLIC HEARING AND RECORD OF DECISION MARCH 2002
OCT 2003 (ROD)
STEP 6² FINAL PROJECT DESIGN PLANS APRIL 2006 - TBD
STEP 7² RIGHT OF WAY ACQUISITIONS AND UTILITY RELOCATIONS UNSCHEDULED
STEP 8² ADVERTISE FOR CONSTRUCTION LETTING UNSCHEDULED
STEP 9 CONSTRUCTION CONTRACT OPEN TO TRAFFIC UNSCHEDULED
¹ - INDICATES PUBLIC INVOLVEMENT
² - INDICATES PRIORITY SECTION